Melview Developments has embarked on the most ambitious hotel and residential construction ever undertaken in the South Island. There are no fewer than 13 buildings to be constructed on Kawarau Falls Station site near Queenstown. Five different architectural firms were commissioned to design the buildings concurrently, sharing a palette of materials but given individual briefs. The result is a cohesive yet diverse stable of structures.

The two storey steel trusses opening out to the courtyard
Design engineer Jeff Clendon of Holmes Consulting Group says that because the structure follows the height restriction plane, the building is partially cut into the ground and has different heights along its length. “The roofs and floor diaphragms span horizontally to distribute earthquake loads to a mixed system of concrete shear walls acting in the transverse, north-south direction, with moment-resisting steel frames acting in the longitudinal, east-west direction. The moment-resisting steel frames extend down the length of the building on the north and south facades, and essentially run from roof level down to level three, which is the lowest “ground” level. The level three diaphragm is connected to the surrounding ground by a series of rock anchors. Below this level, longitudinal basement walls distribute residual earthquake loads to the ground.
“With floor-to-floor heights being at a minimum, steel beam depths were critical; both the composite and non-composite beam design required non-standard solutions in critical areas to maintain head heights. A number of beams required haunches and steel plating to satisfy the design constraints. The roof is typically of lightweight construction, consisting of low-pitched membrane or iron roofing on timber packing over steel purlins and regular steel rafters, with posts to the concrete floors below.”

Prefabricated bathrooms still wrapped in plastic were on a critical path of the construction programme
SCNZ: “What was your biggest challenge in this project?”
Cliff Saunders: “The site resembles a quarry, with no setting down room. This meant we were in deliver-and-erect mode, craning the steelwork straight off the truck and bolting it into position immediately. We even did this with the three trusses, the two biggest of which were 18m long and 6.5m deep. We transported all three as one load, weighing a total of 15 tonnes, from Dunedin to site and got them up the same day. As the project advanced, each finished floor area became our setting down space for the next stage of steel.”
The building provides vehicle and pedestrian access to the adjacent Lakeside West and Lakeside Central West buildings via underground tunnels. The Quadrant Hotel is destined to be a designer 4 star hotel and construction is scheduled for completion by November 2009.






